PMI-001 Q&A – Section 6: Quality Management (51-60)

Section 6: Quality Management QUESTION 51 A new software development project is in progress and the project manager is working with the quality assurance department. They want to improve everyone’s confidence that the project will satisfy the quality standards. Which of the following MUST they have before they start this process? A. Completed checklists B….

Continue reading

PMI-001 Q&A – Section 6: Quality Management (31-40)

Section 6: Quality Management QUESTION 31 A project manager is leading an effort to analyze waste and non-value-added activity on the project. One team member reports that two processes in use require work he believes is unnecessary. Another team member reports that a process is not well understood. The project manager must be leading which…

Continue reading