PMI-001 Q&A – Section 5: Cost Management (111-122)

Section 5: Cost Management QUESTION 111 You are working for an international construction company. Your project involves pulling together over 13 different subprojects. You are having difficulty in ensuring three subcontractors are doing their work correctly. As you review the project results you notice you have spent US $1,200,000 at the last reporting point. You…

Continue reading

PMI-001 Q&A – Section 5: Cost Management (91-100)

Section 5: Cost Management QUESTION 91 A project manager discovers that a work package has been completed for substantially less cost than planned. Which of the following is NOT among the first things to consider doing? A. Make sure all project processes were followed. B. Make sure the right resources were used. C. Make sure…

Continue reading