PMI-001 Q&A – Section 2: Integration Management (111-120)

Section 2: Integration Management QUESTION 111 A stakeholder wants to make a change to the work breakdown structure that does NOT affect the time or cost of the project. What is the BEST thing to do? A. Tell the stakeholder that this change cannot be made without revising the project management plan. B. Make the…

Continue reading

PMI-001 Q&A – Section 2: Integration Management (101-110)

Section 2: Integration Management QUESTION 101 At a critical milestone in a development project, it is determined that implementation is two months behind schedule. The project manager is concerned that the root cause is lack of conformance to requirements in the design of the new billing system. More extensive measurements are taken to see if…

Continue reading