Section 4: Time Management QUESTION 71 You have a project with the following activities: Activity 1 can start immediately and has an estimated duration of 4. Activity 2 can start after activity 1 is completed and has an estimated duration of 8. Activity 3 can start after activity 2 is completed and has an estimated…
Continue readingTime Management
Time Management
PMI-001 Q&A – Section 4: Time Management (61-70)
Section 4: Time Management QUESTION 61 The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT? A. Update resource requirements B. Recommend corrective actions C. Estimate Activity Durations D. Create a milestone list Answer: A
Continue readingPMI-001 Q&A – Section 4: Time Management (51-60)
Section 4: Time Management QUESTION 51 A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here? A. Resource leveling B. Schedule compression C. Critical chain D. Adjusting leads and lags Answer: B
Continue readingPMI-001 Q&A – Section 4: Time Management (41-50)
Section 4: Time Management QUESTION 41 Which of the following is the BEST method of completing “what-if” scenarios to determine what combination of resources and interdependencies will produce the best schedule? A. Critical chain method B. Monte Carlo analysis C. Parametric estimating D. Resource leveling Answer: B
Continue readingPMI-001 Q&A – Section 4: Time Management (31-40)
Section 4: Time Management QUESTION 31 Which of the following processes includes asking team members about the time estimates for their activities and reaching agreement on the calendar date for each activity? A. Sequence Activities B. Develop Schedule C. Define Scope D. Develop Project Charter Answer: B
Continue readingPMI-001 Q&A – Section 4: Time Management (21-30)
Section 4: Time Management QUESTION 21 The precedence diagramming method (activity-on-node) is different from the arrow diagramming method (activity-on-arrow) because a precedence diagram: A. Can use PERT. B. Has four relationships among activities. C. Has only finish-to-finish relationships. D. May use dummy activities. Answer: B
Continue readingPMI-001 Q&A – Section 4: Time Management (11-20)
Section 4: Time Management QUESTION 11 Company A is developing a project similar to one it delivered nearly 12 months earlier. What is the MOST likely approach to defining project activities? A. Review organizational process assets. B. Add similar, if not the same, skill sets to the project team. C. Gather the team for a…
Continue readingPMI-001 Q&A – Section 4: Time Management (1-10)
Section 4: Time Management QUESTION 1 You have just discovered an error in the implementation plan that will prevent you from meeting a milestone date. The BEST thing you can do is: A. Develop options to meet the milestone date. B. Change the milestone date. C. Remove any discussion about due dates in the project…