PMI-001 Q&A – Section 1: Framework and PM Processes (71-80)

Section 1: Framework and PM Processes QUESTION 71 Being told to complete the project in three months using only four resources is an example of: A. Constraints. B. Earned value analysis components. C. Benefit cost ratios. D. Law of diminishing returns. Answer: A Explanation: Limits on what options you have to complete the project are…