Section 2: Integration Management QUESTION 241 Which of the following are ALL outputs of the Perform Integrated Change Control process? A. Approved corrective actions, validated defect repair, forecasts, deliverables B. Deliverables, implemented corrective actions, rejected change requests, validated defect repair C. Approved defect repair, validated defect repair, rejected change requests, approved corrective actions D. Recommended…
Continue readingControl Scope
PMI-001 Q&A – Section 2: Integration Management (221-230)
Section 2: Integration Management QUESTION 221 Which of the following BEST describes the difference between the Control Scope process and the Perform Integrated Change Control process? A. Control Scope focuses on making changes to the product scope and Perform Integrated Change Control focuses on making changes to integration. B. Control Scope focuses on controlling the…