PMI-001 Q&A – Section 5: Cost Management (91-100)

Section 5: Cost Management QUESTION 91 A project manager discovers that a work package has been completed for substantially less cost than planned. Which of the following is NOT among the first things to consider doing? A. Make sure all project processes were followed. B. Make sure the right resources were used. C. Make sure…

Continue reading