Section 2: Integration Management QUESTION 241 Which of the following are ALL outputs of the Perform Integrated Change Control process? A. Approved corrective actions, validated defect repair, forecasts, deliverables B. Deliverables, implemented corrective actions, rejected change requests, validated defect repair C. Approved defect repair, validated defect repair, rejected change requests, approved corrective actions D. Recommended…
Continue readingIntegration Management
PMI-001 Q&A – Section 2: Integration Management (231-240)
Section 2: Integration Management QUESTION 231 Which of the following is NOT a reason to measure variances from the baseline? A. To catch deviations early B. To allow early corrective action C. To determine if there are any wild fluctuations D. To create a project control system Answer: D
Continue readingPMI-001 Q&A – Section 2: Integration Management (221-230)
Section 2: Integration Management QUESTION 221 Which of the following BEST describes the difference between the Control Scope process and the Perform Integrated Change Control process? A. Control Scope focuses on making changes to the product scope and Perform Integrated Change Control focuses on making changes to integration. B. Control Scope focuses on controlling the…
Continue readingPMI-001 Q&A – Section 2: Integration Management (211-220)
Section 2: Integration Management QUESTION 211 The engineering department has uncovered a problem with the cost accounting system and has asked the systems department to analyze what is wrong and fix the problem. You are a project manager working with the cost accounting programs on another project. Management has issued a change request to the…
Continue readingPMI-001 Q&A – Section 2: Integration Management (201-210)
Section 2: Integration Management QUESTION 201 The buyer asks the project manager for the status of the project that his team is working on. What is the BEST way to determine the status of a project? A. Compare the project performance against the project baselines. B. Compare the earned value to the planned value. C….
Continue readingPMI-001 Q&A – Section 2: Integration Management (191-200)
Section 2: Integration Management QUESTION 191 Outputs of the Close Project or Phase process include all of the following EXCEPT: A. Project archives. B. Formal acceptance. C. Lessons learned. D. A risk audit. Answer: D
Continue readingPMI-001 Q&A – Section 2: Integration Management (181-190)
Section 2: Integration Management QUESTION 181 Which of the following BEST describes formal acceptance of a project? A. Substantial completion is reached. B. Customer sign-off of the product is documented. C. Final payment is made. D. Final deliverables are sent to the customer. Answer: B
Continue readingPMI-001 Q&A – Section 2: Integration Management (171-180)
Section 2: Integration Management QUESTION 171 You have a choice of four ongoing projects that you can take over as project manager. Project 1 has a benefit cost ratio (BCR) of 1.4, is a high priority project, and has a critical path length of 16 months. Its cost performance index (CPI) is 1.2. Project 2…
Continue readingPMI-001 Q&A – Section 2: Integration Management (161-170)
Section 2: Integration Management QUESTION 161 The amount of funds available for a company to invest in projects is called: A. Working capital. B. Sunk costs. C. Value analysis. D. Direct cost. Answer: A
Continue readingPMI-001 Q&A – Section 2: Integration Management (151-160)
Section 2: Integration Management QUESTION 151 You have been assigned as the project manager for a construction project that has had two previous project managers, when you discover that a deliverable will be late. Your analysis shows that the item can be purchased from another seller at a higher price without affecting the schedule. What…
Continue readingPMI-001 Q&A – Section 2: Integration Management (141-150)
Section 2: Integration Management QUESTION 141 Your project no longer ties into the company’s objectives. What would be the BEST thing to do? A. Decrease the cost. B. Extend the schedule. C. Change the CPI. D. Change the target opportunity cost. Answer: B
Continue readingPMI-001 Q&A – Section 2: Integration Management (131-140)
Section 2: Integration Management QUESTION 131 Benefit measurement and constrained optimization are examples of: A. Benefit cost ratios. B. Variable costs. C. Types of depreciation. D. Project selection methods.
Continue reading