Section 2: Integration Management QUESTION 161 The amount of funds available for a company to invest in projects is called: A. Working capital. B. Sunk costs. C. Value analysis. D. Direct cost. Answer: A
Continue readingNPV
PMI-001 Q&A – Section 2: Integration Management (151-160)
Section 2: Integration Management QUESTION 151 You have been assigned as the project manager for a construction project that has had two previous project managers, when you discover that a deliverable will be late. Your analysis shows that the item can be purchased from another seller at a higher price without affecting the schedule. What…