Section 4: Time Management QUESTION 41 Which of the following is the BEST method of completing “what-if” scenarios to determine what combination of resources and interdependencies will produce the best schedule? A. Critical chain method B. Monte Carlo analysis C. Parametric estimating D. Resource leveling Answer: B
Continue readingParametric estimating
PMI-001 Q&A – Section 4: Time Management (11-20)
Section 4: Time Management QUESTION 11 Company A is developing a project similar to one it delivered nearly 12 months earlier. What is the MOST likely approach to defining project activities? A. Review organizational process assets. B. Add similar, if not the same, skill sets to the project team. C. Gather the team for a…