PMI-001 Q&A – Section 4: Time Management (41-50)

Section 4: Time Management QUESTION 41 Which of the following is the BEST method of completing “what-if” scenarios to determine what combination of resources and interdependencies will produce the best schedule? A. Critical chain method B. Monte Carlo analysis C. Parametric estimating D. Resource leveling Answer: B

Continue reading

PMI-001 Q&A – Section 4: Time Management (21-30)

Section 4: Time Management QUESTION 21 The precedence diagramming method (activity-on-node) is different from the arrow diagramming method (activity-on-arrow) because a precedence diagram: A. Can use PERT. B. Has four relationships among activities. C. Has only finish-to-finish relationships. D. May use dummy activities. Answer: B

Continue reading