Section 7: Human Resources Management QUESTION 81 The highest point of Maslow’s hierarchy of needs is called: A. Physiological satisfaction. B. Attainment of survival. C. Need for association. D. Esteem. Answer: D Explanation:
Continue readingPMP Exam Questions
PMP Q&A – Section 7: Human Resources Management (41-50)
Section 7: Human Resources Management QUESTION 41 In creating a project management plan, how should a project manager use rewards? A. Use the reward system currently in place throughout the company. B. Ignore rewards because the functional manager will take care of it. C. Create a specific reward system for the project. D. Ignore rewards…