Section 4: Time Management QUESTION 81 The float of an activity is determined by: A. Performing a Monte Carlo analysis. B. Determining the waiting time between activities. C. Determining lag. D. Determining the amount of time the activity can be delayed before it delays the critical path. Answer: D
Continue readingPMP Q&A
PMI-001 Q&A – Section 4: Time Management (71-80)
Section 4: Time Management QUESTION 71 You have a project with the following activities: Activity 1 can start immediately and has an estimated duration of 4. Activity 2 can start after activity 1 is completed and has an estimated duration of 8. Activity 3 can start after activity 2 is completed and has an estimated…
Continue readingPMI-001 Q&A – Section 4: Time Management (61-70)
Section 4: Time Management QUESTION 61 The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT? A. Update resource requirements B. Recommend corrective actions C. Estimate Activity Durations D. Create a milestone list Answer: A
Continue readingPMI-001 Q&A – Section 4: Time Management (51-60)
Section 4: Time Management QUESTION 51 A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here? A. Resource leveling B. Schedule compression C. Critical chain D. Adjusting leads and lags Answer: B
Continue readingPMI-001 Q&A – Section 4: Time Management (41-50)
Section 4: Time Management QUESTION 41 Which of the following is the BEST method of completing “what-if” scenarios to determine what combination of resources and interdependencies will produce the best schedule? A. Critical chain method B. Monte Carlo analysis C. Parametric estimating D. Resource leveling Answer: B
Continue readingPMI-001 Q&A – Section 4: Time Management (31-40)
Section 4: Time Management QUESTION 31 Which of the following processes includes asking team members about the time estimates for their activities and reaching agreement on the calendar date for each activity? A. Sequence Activities B. Develop Schedule C. Define Scope D. Develop Project Charter Answer: B
Continue readingPMI-001 Q&A – Section 4: Time Management (21-30)
Section 4: Time Management QUESTION 21 The precedence diagramming method (activity-on-node) is different from the arrow diagramming method (activity-on-arrow) because a precedence diagram: A. Can use PERT. B. Has four relationships among activities. C. Has only finish-to-finish relationships. D. May use dummy activities. Answer: B
Continue readingPMI-001 Q&A – Section 4: Time Management (11-20)
Section 4: Time Management QUESTION 11 Company A is developing a project similar to one it delivered nearly 12 months earlier. What is the MOST likely approach to defining project activities? A. Review organizational process assets. B. Add similar, if not the same, skill sets to the project team. C. Gather the team for a…
Continue readingPMI-001 Q&A – Section 3: Scope Management (81-90)
Section 3: Scope Management QUESTION 81 Which of the following BEST describes product analysis? A. Working with the customer to determine the product description B. Mathematically analyzing the quality desired for the project C. Gaining a better understanding of the product of the project in order to create the project scope statement D. Determining if…
Continue readingPMI-001 Q&A – Section 3: Scope Management (71-80)
Section 3: Scope Management QUESTION 71 The project is mostly complete. The project has a schedule variance of 300 and a cost variance of -900. All but one of the quality control inspections have been completed and all have met the quality requirements. All items in the issue log have been resolved. Many of the…
Continue readingPMI-001 Q&A – Section 3: Scope Management (61-70)
Section 3: Scope Management QUESTION 61 The customer wants to expand the product scope after the performance measurement baseline has been established. Which document will the customer need to submit? A. Change request B. Project scope statement C. Performance measurements D. Activity attributes Answer: A
Continue reading