Section 1: Framework and PM Processes QUESTION 151 A project may end for all of the following reasons EXCEPT: A. It is determined that the objectives cannot be met. B. The project objectives have been met. C. The need for the project no longer exists. D. The project manager has left the company.
Continue readingprogressive elaboration
PMI-001 Q&A – Section 1: Framework and PM Processes (21-30)
Section 1: Framework and PM Processes QUESTION 21 A project team is working on manufacturing a new product, but they are having difficulty creating a project charter. What is the BEST description of the real problem? A. They have not identified the project objectives. B. They are working on a process and not a project….
Continue reading