PMI-001 Q&A – Section 6: Quality Management (61-70)

Section 6: Quality Management QUESTION 61 The code development phase of a software project is nearly complete when the first code review is conducted. During the review, it is discovered that the application is missing functionality required to complete a key business process. However, the product scope never specified this functionality. What should the project…

Continue reading

PMI-001 Q&A – Section 2: Integration Management (61-70)

Section 2: Integration Management QUESTION 61 If a project manager is concerned with gathering, integrating, and disseminating the outputs of all project management processes, she should concentrate on creating a better: A. WBS. B. Communications management plan. C. Project management information system. D. Project scope management plan.

Continue reading

PMI-001 Q&A – Section 2: Integration Management (51-60)

Section 2: Integration Management QUESTION 51 You are a project manager working on a multimillion-dollar project. As the project has progressed, you have become friends with the general contractor. You are working on a US $100,000 change request. She has offered to let you use her boat on the lake this weekend while she is…

Continue reading

PMI-001 Q&A – Section 1: Framework and PM Processes (41-50)

Section 1: Framework and PM Processes QUESTION 41 During project executing, a project manager from the information systems department is trying to complete the project, yet is constantly faced with interference from the manager of the engineering department. The engineering department keeps changing the resources assigned to the project team and their availability. What type…

Continue reading

PMI-001 Q&A – Section 1: Framework and PM Processes (31-40)

Section 1: Framework and PM Processes QUESTION 31 An organization is going through an evolutionary phase of restructuring the way it does projects. In a shift from a weak matrix organization to a strong matrix organization, the power is shifted from the: A. Project manager to the functional manager. B. Expediter to the coordinator. C….

Continue reading

PMP PMI-001 Exam Questions&Answers Index

PMI-001 Q&A Index (Section 1: Framework and PM Processes) PMI-001 Q&A Index (Section 2: Integration Management) PMI-001 Q&A Index (Section 3: Scope Management) PMI-001 Q&A Index (Section 4: Time Management) PMI-001 Q&A Index (Section 5: Cost Management) PMI-001 Q&A Index (Section 6: Quality Management) PMI-001 Q&A Index (Section 7: Human Resources Management) PMI-001 Q&A Index…

Continue reading